What is the typical lead time for a Custom Engineered solution?

HYSF is known for Rapid Prototyping. While international competitors often quote 16-24 weeks for custom work, our typical lead time for a new design is 4-6 weeks from design approval to first article shipment. Simple modifications can often be done in 2-3 weeks.

Speed is part of our competitive advantage (“Import Substitution”).

  • In-House Tooling: We have our own mold-making shop and CNC centers, allowing us to machine prototypes overnight without waiting for external vendors.
  • Agile Process:
    1. Week 1: Requirement analysis & 3D CAD design.
    2. Week 2: Client approval & Mold machining.
    3. Week 3-4: Production of samples, vulcanization, and pressure testing.
    4. Week 5: Shipment.
Image de John Zhang

John Zhang

(CEO & Lead Engineer)
Courriel : info@hysfsubsea.com
With over 15 years of expertise in subsea interconnect technology, I lead HYSF's R&D team in designing high-pressure (60MPa) solutions. My focus is on ensuring zero-leakage reliability for ROVs, AUVs, and offshore instrumentation. I personally oversee the validation of our custom connector prototypes.

Have a complex technical question?

Des solutions éprouvées sur le terrain

Une vitrine de nos collaborations fructueuses avec des partenaires mondiaux dans les domaines de la robotique marine, de l'énergie et de la recherche. Chaque projet reflète notre engagement en faveur d'une intégrité sans fuite et d'une fiabilité opérationnelle.

Lancez votre projet sous-marin avec HYSF

Que vous ayez besoin d'un devis rapide pour des connecteurs standard ou d'un assemblage complexe de câbles sur mesure, notre équipe d'ingénieurs est prête à vous aider. Une réponse technique est attendue dans les 12 heures.

John Zhang

PDG

Jason Liu
Kevin Wang
Cindy Chen
Lily Li
Démonstration du formulaire de contact