현장 스플라이싱은 케이블 조립 실패의 #1 원인입니다.
- Risk: A manual splice is rarely as robust as the factory 고온 가황 bond.
- Water Blocking: If you must splice, ensure you do not compromise the water-blocking gel/filler inside the cable.
- Recommendation: Measure twice, order once. Let us manufacture the cable to your exact length (e.g., 5.5 meters) to avoid the need for splicing entirely.